Practical guide

Check a turnover window and budget reserve

A turnover plan has two constraints: the work must fit the entered departure-to-arrival window, and the estimate must fit the approved budget. TurnKey shows both comparisons.

Calculate available work hours

The tool counts whole days between departure and arrival and multiplies by workday hours. The default 2026-10-01 to 2026-10-03 window at 8 hours per day provides 16 planning hours, so 15 task hours fit the window.

available work hours = (arrival date - departure date) x workday hours per day

Apply the reserve after line items

The default 460 itemized subtotal receives a 10% reserve, producing 506 before any other entered adjustments. Replace the illustrative rows and reserve when the scope changes.

The reserve is a visible percentage of the itemized estimate, not an untracked extra line.

Read the budget warning

The default estimate is 1,248.50 against a 900 budget, leaving negative 348.50 budget headroom. Use the difference to revisit scope, labor rate, or approved budget assumptions.

Check your own scenario

Replace the illustrative inputs with measured values and dated specifications.

Open TurnKey Turnover

Method and references

Read the full calculation method and its limits

Method and examples reviewed 2026-09-30. Examples are illustrative; input values and specifications are not independently verified.